08 February 2017
Now that construction of cycle lanes is finally under way, Enfield Council will shortly be making announcements about the other important aspect of its Cycle Enfield/Mini Holland project - measures to set up a network of Quieter Neighbourhoods throughout the borough.
Two of the planned Quieter Neighbourhoods in Palmers Green. Click on the map to enlargeWork on developing Quieter Neighbourhoods - involving measures to reduce the amount of traffic in residential side streets, and in.......
Read the full article
03 February 2017
The latest news about the Triangle from Richard Eason, Cycle Enfield Consultation Manager, is that the plans include six new trees. Five of these are intended to be ‘heavy standard’ trees (three located around HSBC and two by Starbucks). The sixth tree will be a semi-mature tree to be placed in the middle of the triangle.
So essentially as captured in the attached visualisation, though the positioning of the clock is yet to be agreed.
Work on the triangle is currently scheduled.......
Read the full article
and forum comments
01 February 2017
According to a letter delivered to homes in the vicinity of the A105, Cycle Enfield construction work in Palmers Green was due to start "by late January 2017" between Lodge Drive and Osborne Road. Work on this section would continue until June.
17th January 2017
Cycle Enfield construction on the A105
This letter is to inform you of work in your area to construct the A105 cycle lane.
Work on the upcoming sections of the cycle route (between Lodge Drive and Osborne Road and also.......
Read the full article
and forum comments
18 January 2017
Because of delays caused by the Cycle Enfield road works along the A105, the 329 bus is currently not running south of Wood Green station. This will allow frequencies to be retained between Palmers Green and Enfield. According to the TfL website, the route curtailment runs from 5th January to 30th March.
Southbound buses are terminating very close to the usual stop outside Wood Green station. However, buses towards Palmers Green on the 329 are not serving the northbound Wood.......
Read the full article
14 December 2016
Waltham Forest's "village" traffic management schemes have been highly successful. Hopefully, Enfield's road planners will be equally ambitious when they restart work on Quieter Neighbourhoods.
As 2016 draws to a close it's good to see work finally under way to restore to people the freedom to travel along Green Lanes by bicycle safely and securely - a freedom that has been increasingly denied for the past fifty or sixty years. Of all ways of travelling, apart from walking,.......
Read the full article
20 November 2016
The Cecil Road/Church Street junction - an excerpt from the detailed drawingsMore information about the revised Enfield Town section of Cycle Enfield are now available on the Cycle Enfield website. See this earlier report for an overview of the new scheme.
The following downloads are now available on this page
Revised Option Design
Predictive Equalities Impact Assessment
Young People Summer Engagement Report
Design Surgery Report
Air Quality Assessment
Economic Impact Assessment.......
Read the full article
09 November 2016
Revised Proposals and Timetable
Summary and map on Cycle Enfield website
January 2017: Exhibition of revised proposals and community co-design workshops for enhanced public realm
Spring 2017: Statutory consultation to capture any final issues that may impact upon the design
Enfield Council has today revealed its revised proposals for implementing its Cycle Holland vision in the centre of Enfield Town.
The new scheme retains the existing one-way system for cars, buses and.......
Read the full article
and forum comments
15 October 2016
Roadworks aren't usually popular with residents. So workers in Ridge Avenue, Winchmore Hill, had a surprise on Friday morning when local parents came to say “Thank you for the bike lanes”, bringing with them a cooked breakfast.
Palmers Green residents Clare Rogers, Claire Brady and Maggie Westhead, who all have children at schools in the borough, brought bacon rolls, pastries, tea, coffee and fruit juice for the workers' 10am tea break. They also displayed a homemade “Thank.......
Read the full article
02 September 2016
Enfield Council's plans to install cycle lanes along the A105 are again being challenged, this time by Conservative councillors, who have "called in" the decision by the Cabinet Member for the Environment, Councillor Daniel Anderson, to implement the proposals as set out in the Statutory Consultation earlier this year........
Read the full article
27 August 2016
Enfield Council's plans for cycle lanes along main roads and quieter neighbourhoods in residential areas moved a little closer to completion this week, when a High Court judge refused an application for a judicial review of the Cycle Enfield consultation arrangements and ordered that the Save Our Green Lanes campaigning group should pay the Council's costs.
The judge dismissed claims by the anti-cycle lane campaigners that there were serious flaws in the way the consultation was.......
Read the full article
and forum comments
28 July 2016
The Stage 1 Road Safety Audit for the A105 cycle lanes scheme has now been published. The auditors, from Transport for London (TfL), have indicated that they are satisfied with the responses to all the safety issues that they raised. Unfortunately, the auditors did not comment on hazards for pedestrians crossing roads at the Green Lanes/Hedge Lane/Bourne Hill junction, presumably because their terms of reference state that "Safety Audit is not intended to identify pre-existing.......
Read the full article
06 July 2016
The Cycle Enfield A105 project has now reached the Statutory Consultation stage, which runs from today (6th July) until 29th July. This gives the public an opportunity to submit formal objections to the entire scheme or individual elements. Enfield Council will be distributing information leaflets to homes and businesses.
All required documents are linked to from cycleenfield.co.uk/major-projects/a105-scheme-consultation.
Paper copies of these documents are also available for.......
Read the full article
06 July 2016
The debate about Enfield’s Mini Holland rages on via social media and the local press – will there be gridlocked roads? Vacant businesses? Cyclists mowing down the elderly at bus stops? Meanwhile, some of us from Better Streets for Enfield and Enfield Cycling Campaign decided it would be easiest just to go and look at a Mini Holland that’s already in progress. Waltham Forest is, after all, next door to us, and ahead of Enfield in completing the work.
Read the full article
04 July 2016
A 12-week consultation has begun giving residents an opportunity to give their views on proposals for cycle lanes along the A1010 between Ponders End and Freezy Water. Meanwhile, Enfield's Cabinet will this week be asked to approve the start of detailed design work for the southern section of the A1010.
A1010 North Consultation
Drawings of the proposals for the Ponders End - Freezy Water section are available online. It is possible to give your views using the Citizen Space.......
Read the full article
30 May 2016
Opponents of Enfield Council's cycle lanes proposals have initiated legal action aimed at stopping implementation of plans for cycle lanes along the A105.
The Save Our Green Lanes campaign last week served the council with papers in connection with its application for a High Court judicial review of the way the council has conducted consultations about the scheme, which envisages the creation of continuous cycle lanes between Enfield Town and Palmers Green.
Costas Georgiou, Chairman of the.......
Read the full article
24 May 2016
The revised drawings for the planned cycle lanes along the entire length of the A105 between Enfield Town and Palmers Green are now available online. The drawings reproduced below show the most important sections in Palmers Green only.
In addition to the drawings the Council has published a "You said - we did" list:
You Said - We Did
You were concerned about the bus stop design – we have amended the design at 22 bus stops to create additional space between the bus and the.......
Read the full article
17 May 2016
A new campaigning group is calling for a fairer balance between cars, cycles, buses and pedestrians on Enfield's roads. Better Streets for Enfield supports the Cycle Enfield (Mini Holland) plans to boost cycling and walking rates by installing bike lanes, 'quieter neighbourhoods', and redesigned high streets.
Devonshire Road should by rights be a quiet residential street, but most of the time is a "rat run". For two hours a month it turns into a Play Street (Photo: Phil Rogers)While.......
Read the full article
04 May 2016
On 19th May Enfield Council will be exhibiting the final design plans for the A105 cycle lanes scheme, revised to take account of public feedback from the last consultation round. The exhibition will be held at Palmers Green Library from 3pm to 8pm.
On the evening of Wednesday 25 May there will be a co-design workshop for residents on the design of the public realm mprovements in Palmers Green and Winchmore Hill. People have to apply for a limited number of places on this workshop, so get.......
Read the full article
and forum comments
15 April 2016
Clare Rogers shares her thoughts about last week's Enfield Cycling Conference
This conference at Enfield’s Dugdale Centre on Friday 8 April left me feeling both inspired and daunted – inspired because we were shown what is possible and already being done in the Netherlands – and daunted because Enfield has such a long way to go.
This post tries to give a taste of what was said at the conference. For more in-depth information, you can find links to each presentation.......
Read the full article
11 February 2016
Text and images (with some slight reformatting) taken from the Cycle Enfield website and the A105 Consultation Report.
The bus stop bypass and bus stop boarder designs that are proposed have been used in other parts of London and the UK. There are a number of councils who have implemented these designs (e.g. Camden Council and Brighton & Hove Council) who have monitored their impact and have not reported any significant issues.
Whilst it is acknowledged that this is a design not previously.......
Read the full article