Paul Rogers, Programme Manager for Cycle Enfield in Enfield Council's Planning, Highways and Transportation division, has provided the following high level programme dates for the A105 Enfield Town to Palmers Green.
Activity |
Start Date |
Finish Date |
Preliminary design |
13/11/14 |
22/04/15 |
Modelling |
17/07/14 |
08/07/15 |
Consultation |
27/11/14 |
04/11/15 |
Scheme approval |
20/08/15 |
16/12/15 |
Detailed design |
24/09/15 |
23/03/16 |
Implementation |
10/03/16 |
29/09/16 |