Share share on facebook share on twitter share on Bluesky

Below is a brief description of the progress of work in each of the area we are currently working. It is not an exhaustive list and may be subject to change due to adverse weather conditions.

A105 Scheme

Green Dragon Lane to York Road –The zebra crossing is now complete and has been reopened.

Borden Avenue to Walnut Grove – The final section of line marking and cycle segregation units will be installed in the coming week. The bus shelter outside the church has been removed and the new one installed awaiting electrical connection. Three shared parking bays are also currently being constructed and will be completed next week.

Green Dragon Lane to York Road –The zebra crossing is now complete and has been reopened.

Borden Avenue to Walnut Grove – The final section of line marking and cycle segregation units will be installed in the coming week. The bus shelter outside the church has been removed and the new one installed awaiting electrical connection. Three shared parking bays are also currently being constructed and will be completed next week.

Green Dragon Lane to York Road –The zebra crossing is now complete and has been reopened.

Borden Avenue to Walnut Grove – The final section of line marking and cycle segregation units will be installed in the coming week. The bus shelter outside the church has been removed and the new one installed awaiting electrical connection. Three shared parking bays are also currently being constructed and will be completed next week.

Sainsbury’s Junction – The traffic signals at the junction have been installed and are awaiting final commissioning by Transport for London which is currently scheduled for 28 April. 11 May. Work is expected to be complete by the mid-May.

Station Road Junction – The traffic signals are awaiting final commissioning by Transport for London which is currently scheduled for 11 May. Work is continuing with lane marking, kerb lines and paving slabs. Three central islands have been installed and will be completed in the coming week. Work will continue on the installation of kerb lines, paving work and cycle lane. The work on this section is scheduled to be complete by mid May 2017.

Church Street Junction with Bush Hill Road – We are currently constructing additional footpath area behind the bus stops. We will soon be installing a rain garden.

Most new street lighting has now been commissioned. Work on this section is expected to be complete by late April.

Lodge Drive to Osborne Road –  We will be working between Bourne Hill/Hedge Lane and Fox Lane roundabout in order to install the new cycle path. We will also be installing drainage, paving, signalling and a new bus boarder. More parking spaces have been made available for business customers in this area. The construction of a new bus boarder stop will start next week. Work on this section is scheduled to be completed by late May 2017.

Radcliffe Road to Riverbank – We are installing a new kerb line, cycle lane and paving as well as improving drainage and constructing rain gardens. The work on this section is scheduled to be completed by mid June 2017.

Oaktree Avenue to Highfield Road – Work to complete a further bus stop near Fernleigh Road continues. Temporary pedestrian signals will remain place until the new crossing is commissioned.

Bush Hill to Essex Road – Work will continue to install new drainage and we will start to build the cycle lane. Work is expected to be complete by August.

Ecclesbourne to Oakthorpe Road - Work is continuing on Palmerston Crescent northbound working north. We will be working on the installation of kerbs, concrete slabs and drainage.  In order to carry out work safely, Broomfield Lane will be closed from Monday 24 April for four weeks.

Ponders End scheme

High Street – The northern section between Eagle House Car Park and Stonehorse Road will be constructed in the first half of the calendar year. The southern section between Stonehorse Road and Clarence Road will be built in the second half of the calendar year. The challenging reconfiguration of the Derby Road junction is being planned for the summer holiday period to minimise disruption.

Queensway - Associated works are planned for Queensway to improve pedestrian access to the new school. The work to improve the footways and add a zebra crossing started earlier this month. This section is not expected to affect the wider traffic network.

To see the work schedules for all projects including those not yet started please visit our Construction page.

Log in to comment