Paul Rogers, Programme Manager for Cycle Enfield in Enfield Council's Planning, Highways and Transportation division, has provided the following high level programme dates for the A105 Enfield Town to Palmers Green.

Activity

Start Date

Finish Date

Preliminary design

13/11/14

22/04/15

Modelling

17/07/14

08/07/15

Consultation

27/11/14

04/11/15

Scheme approval

20/08/15

16/12/15

Detailed design

24/09/15

23/03/16

Implementation

10/03/16

29/09/16