Cycle Enfield's latest consultation and construction update
Below is a brief description of the progress of work in each of the area we are currently working. It is not an exhaustive list and may be subject to change due to adverse weather conditions.
Green Dragon Lane to York Road
Most substantive work on this section is complete. Additional tree planting will take place until mid-March.
Borden Avenue to Walnut Grove
We will be removing and replacing a bus shelter, completing drainage work as well as replanting the flower beds and planting a new tree outside the church. Resurfacing of this section is expected to start the week commencing 27 February and is scheduled to be completed by 7 March.
During this work the following side roads will be closed overnight: Borden Avenue, Conifer Gardens, Teynham Avenue, Park Avenue, Sittingbourne Avenue, Faversham Avenue, Mortimer Drive, Regency Court Walnut Grove and the Green Lanes between Walnut Grove and Borden Avenue.
A diversion map is available here.
Work is expected to be complete by the end of March.
Sainsbury’s Junction
Upcoming work includes the building of the bus stop, the installation of segregation island and central islands to assist safer crossings, as well as the commissioning of signals.
Work to lay a new surface for the main carriageway on Green Lanes between Carpenter Gardens and Queen’s Avenue (A105) will take place overnight, between 10pm and 6am, for one night starting on the evening of Friday 24 February.
Please note that Highfield Road and the Sainsbury’s entrance will be closed to vehicles during this work .
A diversion map is available here.
Work is expected to be complete by mid March.
Station Road Junction
Work will start on the installation of kerb lines, paving work and vital drainage engineering. In addition, work will begin on the cycle lane, as well as introducing some new green space.
The work on this section is scheduled to be complete by late May 2017.
Church Street junction with Bush Hill Road
We are currently installing segregation and central islands to make pedestrian crossings safer, as well as installing signals and completing drainage works.
Work on this section is expected to be complete by mid April.
Lodge Drive to Osborne Road
Starting in early February we will be working between Bourne Hill/Hedge lane and Fox lane roundabout in order to install new kerb lines along this area. We will also be installing drainage, paving and signalling. Work on this section is scheduled to be completed by mid September 2017.
Radcliffe Road to Riverbank
Over the next two weeks we will be installing a new kerb line and cycle lane as well as improving drainage.
The work on this section is scheduled to be completed by mid June 2017.
To see the work schedules for all projects including those not yet started please visit our Construction page here.